Huge Progress Made On The Felixstowe Branch Line To Increase Freight Traffic

Published on : Saturday, December 29, 2018

Network RailRail engineers have worked over the festive period on the Felixstowe branch line as part of Network Rail’s £60m project to install a new 1.4km loop near Trimley which will enable increased freight traffic and improve reliability for passenger services.

 

As well as upgrading the signalling power system, three new track crossings, which enable trains to switch from one track to another, have been installed as part of the work to provide 1.4km of extra railway line between Trimley and Gun Lane, enabling the running of trains on the new railway in mid 2019.

 

The new track will support up to 10 additional freight trains in each direction per day, moving goods to and from the Port of Felixstowe. Passengers will also benefit from improved reliability for existing services between Felixstowe and Ipswich.

 

With each additional freight train taking the equivalent of up to 76 lorries off the roads, the upgrade works will help to reduce congestion and pollution for the local community and the wider region. The work also includes upgrades to four road level crossings between Trimley and Westerfield which will improve public safety while allowing more trains to run on the line.

 

Across the country, a 25,000-strong workforce are working more than 380,000 hours to keep the railway open and deliver 330 projects.

 

The work is being completed at the quietest time for rail travel on the country’s railway with around half the normal number of passengers travelling compared to the 4.7 million who typically use the network daily.

 

Meliha Duymaz, Network Rail’s route managing director for Anglia, said: “We have used the quieter Christmas period to progress this new section of track which will improve the strategic freight network as part of our Railway Upgrade Plan. This work is essential to increase the number of freight services using the railway while also improving reliability for passengers.”

 

Further works are taking place across the region’s rail network until Wednesday 2nd January, including installing a new overhead wiring system at Forest Gate on the line from London to Norwich to improve reliability and reduce delays and cancellations.

 

Source:- Network Rail

Tags:

Leave a Reply

Your email address will not be published. Required fields are marked *

arrow2Follow TTW
 
facebook-logo  twitter-logo  LinkedIn_logo  stumbleupon-logo   rss_logo 
ttw_blogger_logo  ttw_blogger_logo  ttw_blogger_logo

ADVERTISEMENT

  • 08 imexamerica 2019
  • 13 Food Hospitality2019
  • 14 Hotelierseries Africa 2019
  • 14 restaurantscafeslounges 19
  • 16 global-hotels-resorts 2019
  • 16 TTF 2019
  • 17 getglobal 19
  • 18 Africa Hotel & Resort 2019
  • 18 chinatravelnews2019
  • 18 MILT 2019
  • 19 China Hotel 19
  • 30 PATA

TRAVEL INDUSTRY EVENTS

    1. THE HOTEL SHOW AFRICA

      June 23 - June 25
    2. DIGITAL TRAVEL SUMMIT

      June 25 - June 26
    3. 29th ACI EUROPE Annual Assembly & Congress

      June 25 - June 27
    4. TTF SOUTH (HYDERABAD)

      July 5 - July 6
    5. HOTEL SUMMIT

      July 8 - July 9
Get our toolbar!
Review www.travelandtourworld.com on alexa.com