Network Rail Responds To National Audit Office Report Into Tram Train pilot

Published on : Wednesday, July 5, 2017

Network RailRob McIntosh, Network Rail’s London North Eastern and East Midlands Route Managing Director, said: “Sheffield to Rotherham tram-train is an ambitious pilot, a UK first, that will bring new travel choices to people of South Yorkshire when services begin in 2018. The project continues to be complex and challenging but will deliver real benefits for thousands of daily commuters.

 

 

“Costs and timescales have moved as the project itself has grown in scope and complexity and has had to incorporate more significant infrastructure changes than originally planned. Good progress is being made and a new project team is now in place and driving the scheme to its conclusion.”

 

 

Over the past year all of the track and junctions connecting the tramway and railway have been installed and the erection of overhead masts between Tinsley and Parkgate, completed. Work has also started on the construction of the new tram-train platform at Parkgate, and work continues to raise College Road bridge to allow the overhead power lines to pass underneath.

 

 

Mr McIntosh continued: “The project has learned from tram-train systems in Europe that have encountered their own challenges but there were still a significant number of unique issues to the UK that had to be overcome.”

 

 

An example of this is the electrification system, which uses DC power as opposed to the AC system which is used across the majority of our network. The pilot has deliberately taken significant time to robustly test and investigate the best way to provide this system.

 

 

Similarly the project has been extended to include additional work to future-proof the tram-train electrification system for later conversion to the national rail standard system that was not part of the original scope. Such factors have added time and cost to the pilot which is under significant pressure to deliver a much-anticipated service for the local community and our partners.

 

 

Mr McIntosh concluded: “As acknowledged by the NAO, significant changes have been made to the management of the project, with a number of construction milestones achieved, new expertise has been added to the project team and a new, more robust schedule of works created.

 

 

“Upcoming milestones include the completion of the tram-train stops at Rotherham Central and Parkgate and the completion of the overhead line power system. We look forward to continuing to work with our partners to enable the introduction of a full tram-train service for passengers in 2018.”

 

Source:- Network Rail

Tags:

Leave a Reply

Your email address will not be published. Required fields are marked *

*

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>

arrow2Follow TTW
 
facebook-logo  twitter-logo  LinkedIn_logo  stumbleupon-logo   rss_logo 
ttw_blogger_logo  ttw_blogger_logo  ttw_blogger_logo

ADVERTISEMENT

  • 03 itb-asia 2017
  • 04 Imex America 2017
  • 10 Globalwellnesssummit 2017
  • 11 AHIF 2017
  • 12 TTF17
  • 13 Frontiers Forum 2017
  • 14 bltm 2017
  • 15 leisure 17
  • 16 SKAL 17
  • 17 hospitalityqatar 17
  • 17 worldmiceday 2017
  • 18 TRAVEL-TECH-MIDDLE 2017
  • 18 worldmiceday 2017
  • 19 IITM
  • 19 TTG Incontri 2017
  • 43 PATA

TRAVEL INDUSTRY EVENTS

Get our toolbar!
Review www.travelandtourworld.com on alexa.com