Rail Services Resume As Multimillion-Pound Project To Railway In Derbyshire Successfully Completed

Published on : Monday, February 18, 2019

Network RailNetwork Rail has successfully completed a £13million pound investment into the railway in the Derwent Valley area – with all services between Derby and Matlock resuming on schedule.

 

 

For the last six says, Network Rail engineers have been working round the clock to renew and relocate Ambergate Junction, the point where the Matlock branch leaves the Midland Main Line, as well as carry out upgrades to the signalling. The work was part of the Midland Main Line Upgrade and will mean trains can travel through the area at higher speeds.

 

 

The project meant coach replacement services for passengers travelling between Matlock and Derby and changes to East Midlands Trains and CrossCountry services. The project completed on time with train services resuming this morning and the end of the coach replacement services and journey time impacts imposed by train diversion routes.

 

 

Rob McIntosh, Route Managing Director for Network Rail, said: “We are delighted that this vital work, which will allow trains to travel at an increased speed, is now complete.

 

 

“We worked extremely closely with East Midlands Trains CrossCountry to keep passengers moving and we’d like to thank passengers for their patience whilst this work took place.

 

 

“This work is the latest stage of the Midland Main Line Upgrade, which is the biggest investment into the railway in this area since it was built in the Victorian era. This major project will improve journeys for all passengers using the line and will ensure we can continue to provide a service which meets the needs of the communities and economies that our railway serves.”

 

 

Jake Kelly, Managing Director for East Midlands Trains said: “The Ambergate Junction represents another major milestone towards improving the railway in the East Midlands.

 

 

“We worked alongside Network Rail to minimise the disruption as much as possible, but we know that it impacted on our customer’s journeys, and we would like to thank our customers for their continued support whilst this work has been taking place.”

 

 

CrossCountry’s Production Director, Andre Cnossen, said: “We would like to thank our customers for their patience while this latest investment to improve the railway in Derbyshire was completed. This work by Network Rail will benefit rail users for years to come, and we are already preparing to introduce faster and more reliable journeys for our customers in future timetables.”

 

Source:- Network Rail


(No Like Yet)

Related Posts

Tags:

Comments are closed.

arrow2Follow TTW
 
facebook-logo  twitter-logo  LinkedIn_logo  rss_logo 
ttw_blogger_logo  ttw_blogger_logo

ADVERTISEMENT

  • 03 ITB Asia 2021
  • 08 iitm 2021
  • 12 ttfotm 2021
  • 13 aaaexpos 21
  • 14 KITF 2021
  • 15 MENA 2021
  • 16 atwconnect 21
  • 16 ITB asia 2020
  • 18 globalwellnesssummit  21
  • 30 PATA

TRAVEL INDUSTRY EVENTS

    1. INTERNATIONAL HOSPITALITY INVESTMENT FORUM (IHIF)

      March 8 - March 10
    2. ITB Berlin

      March 10 - March 14
    3. SALON DESTINATIONS NATURE 2020

      March 18 - March 21
    4. Arabian Travel Market

      May 16 - May 19
    5. IMEX FRANKFURT

      May 25 - May 27
Get our toolbar!
Review www.travelandtourworld.com on alexa.com